1. Which of the following is NOT a characteristic of a project?

a) Temporary
b) Unique
c) Ongoing
d) Progressive

Answer: c) Ongoing

2. Which of the following is NOT a process in the Project Integration Management knowledge area?

a) Develop Project Charter
b) Develop Project Management Plan
c) Direct and Manage Project Work
d) Close Project or Phase

Answer: c) Direct and Manage Project Work

3. Which of the following is NOT a tool or technique used in the Control Quality process?

a) Inspection
b) Statistical sampling
c) Pareto chart
d) Resource leveling

Answer: d) Resource leveling

4. Which of the following is NOT a component of the Project Scope Statement?

a) Project objectives
b) Project deliverables
c) Project constraints
d) Project assumptions

Answer: d) Project assumptions

5. Which of the following is NOT a type of power in the Project Stakeholder Management knowledge area?

a) Expert power
b) Reward power
c) Referent power
d) Coercive power

Answer: b) Reward power

6. Which of the following is NOT a process in the Project Risk Management knowledge area?

a) Plan Risk Management
b) Identify Risks
c) Perform Qualitative Risk Analysis
d) Control Risks

Answer: d) Control Risks

7. Which of the following is NOT a tool or technique used in the Estimate Costs process?

a) Analogous Estimating
b) Parametric Estimating
c) Bottom-up Estimating
d) Resource Breakdown Structure

Answer: d) Resource Breakdown Structure

8. Which of the following is NOT a component of the Project Communications Management knowledge area?

a) Plan Communications Management
b) Manage Communications
c) Control Communications
d) Monitor Communications

Answer: d) Monitor Communications

9. Which of the following is NOT a type of dependency in the Project Schedule Management knowledge area?

a) Finish-to-Start
b) Start-to-Start
c) Finish-to-Finish
d) Start-to-Finish

Answer: d) Start-to-Finish

10. Which of the following is NOT a tool or technique used in the Conduct Procurements process?

a) Bidder conferences
b) Proposal evaluation techniques
c) Contract change control system
d) Make-or-buy analysis

Answer: c) Contract change control system

立即咨询答疑
关注官方微信 关注官方微博

注:本站稿件未经许可不得转载,转载请保留出处及源文件地址。

精品考试课程

  • PMP考试培训 特训PMP®考试培训

    可能关注:报考条件,备考策略,报考流程

    课程名称:PMP项目管理认证

    获取学习资料
  • Acp考试培训 热门Acp考试培训

    可能关注:新版考纲,经验分享,报考知识,含金量

    课程名称:敏捷项目管理认证

    获取学习资料
  • Npdp考试培训 热门Npdp考试培训

    可能关注:报考条件,学习内容,上课方式,含金量

    课程名称:产品经理国际资格认证

    获取学习资料
  • 软考直播课 热门软考直播课(中、高级)

    适合对象:项目主管,企业中高层,部门经理,工程师

    好处优势:职称评定、升职加薪;户籍加分,扎根落户

    获取学习资料

PMP培训学习资料获取

PMP报考条件是什么?

考试难度了解,学习计划制定,报考条件及费用

来电了解 ☏ 138-1158-4615>
PMP考试收费标准